Step | | Procedure & Parts & Tools |
1 |
|
MAKE SURE THERE IS WATER IN TANK. TURN MACHINE ON AND ACTIVATE THE SOLUTION SYSTEM (DROP DECK AND DRIVE FORWARD FOR A BIT TILL THE PUMPS ENGAGE)
|
2 |
|
CHECK SOLUTION LINE AND DRAIN HOSE AT BACK LOWER LEFT CORNER FOR LEAKS. TURN SOLUTION SYSTEM OFF
|
3 |
|
LOCATE THE DRAIN HOSES ON BACK OF MACHINE
|
4 |
|
PULL THE BLUE CAPPED DRAIN HOSE FROM MACHINE TO INSPECT FOR LEAKS.
|
5 |
|
PULL THE BLACK CAPPED DRAIN HOSE FROM MACHINE TO INSPECT FOR LEAKS
|
6 |
|
PLACE HOSES NEAR DRAIN AND REMOVE THE CAPS TO DRAIN THE TANKS
|
7 |
|
LOCATE THE 2 TANK BOLTS AT THE FRONT BASE OF MACHINE. REMOVE THE 2 TANK BOLTS ON EACH SIDE OF BASE (SET BOLTS ASIDE)
Ratchet-Socket metric 13mm |
|
|
8 |
|
LIFT THE FRONT OF THE TANK TO OPEN THE MACHINE AND LOCATE THE BATTERIES
|
9 |
|
REMOVE THE BATTERIES FROM THE MACHINE AND LOWER TANK TO CLOSE MACHINE (NO NEED TO REINSTALL TANK BOLTS AT THIS TIME)
|
10 |
|
LAY THE MACHINE ON IT'S SIDE AND LOCATE ALL SOLUTION LINES UNDER MACHINE
|
11 |
|
VISUALLY INSPECT ALL THE SOLUTION HOSES AND FITTINGS FOR LEAKS. FEEL HOSES TO SEE IF WET.
|
12 |
|
STAND MACHINE UPRIGHT, REINSTALL BATTERIES, REINSTALL TANK BOLTS AND FILL TANK WITH WATER AND SOLUTION IF NEEDED
Ratchet-Socket metric 13mm |
|
|